*Last updated November 20th, 2009
SATURDAY NOVEMBER 14, 2009 (NO WORK)
DAY: Work Shift Is From 8:00 am to 5:00 pm
SUNDAY NOVEMBER 15, 2009 (NO WORK)
DAY: Work Shift Is From 8:00 am to 5:00 pm
MONDAY NOVEMBER 16, 2009
DAY: Work Shift Is From 7:00 am to 7:00 pm
Operation #1 No work
Location: Liberty St. From: Nassau St. – William St.
Operation #2 Substantially completed (No work)
Location: Pearl St. From: John St. – Fulton St.
Operation #3 Drilling and Grouting operations
Location: Louise Nevelson Plaza From: Liberty St. from William St. –Gold St.
Operation #4 Sidewalk and vault modification on north side
Location: Maiden Lane From: Pearl St. – Water St.
Operation #5 Install road base, utility relocation continues
Location: Maiden Lane From: Pearl St –Gold St. /Intersection
Operation #6 Utility relocation, road base curb and sidewalk
Location: Liberty Street From: Gold St. - William St
TUESDAY NOVEMBER 17, 2009
DAY: Work Shift Is From 7:00 am to 7:00 pm
Operation #1 No work
Location: Liberty St.
From: Nassau St. – William St.
Operation #2 Substantially completed (No work)
Location: Pearl St.
From: John St. – Fulton St.
Operation #3 Drilling and grouting operations
Location: Louise Nevelson Plaza
From: Liberty St. from William St. –Gold St.
Operation #4 Sidewalk and vault modification on north side
Location: Maiden Lane
From: Pearl St. – Water St.
Operation #5 Install road base, utility relocation continues
Location: Maiden Lane From: Pearl St –Gold St. /Intersection
Operation #6 Utility relocation, road base curb and sidewalk
Location: Maiden Lane From: Gold St. - William St.
------------------------------------------------------------------------------------------------------
NO MAJOR CONSTRUCTION ACTIVITIES TO OCCUR IN THE FOLLOWING LOCATIONS:
Liberty Street between Nassau Street and Gold Street Maiden Lane between William Street and Water Street Louise Nevelson Plaza Monday, November 23, 2009 thru Sunday, November 29, 2009
Beginning on/about Monday, November 23, 2009, and continuing through Sunday, November 29, 2009, there will be no major construction activities occurring at the following locations: Liberty Street between William Street and Gold Street; Maiden Lane between William Street and Pearl Street; and, Pearl Street between John Street and Fulton Street. Work activities will resume on Monday November 30, 2009.
Traffic / Community Impacts:
We appreciate your cooperation and thank you for your patience while we rebuild Manhattan’s infrastructure.
------------------------------------------------------------------------------------------------------
The DDC Continues Work on Liberty Street
The New York City Department of Design and Construction (NYCDDC) is managing a capital construction project along Liberty Street between Nassau and Gold Streets, Maiden Lane between William and Water Streets and Pearl Street between Fulton and John Streets. In addition, the Louise Nevelson Plaza will be reconstructed.
WORK COMPLETED AS OF August 2009
Below is a list of work locations and activities that have been completed to date:
Location 1: Liberty Street (Nassau Street–William Street):
Location 2: Pearl Street (Fulton Street- John Street):
Location 3: Louise Nevelson Plaza:
- Excavation of the sub-grade of the plaza.
- Installation of the artwork piece “Rainbow conversations” on the fencing surrounding Plaza.
WORK SCHEDULED for September- October 2009:
Below is a list of work locations and activities slated to occur / to be completed:
Location 1: Liberty Street (Nassau Street–William Street):
- Begin sidewalk replacement
Location 2: Pearl Street (Fulton Street- John Street):
Location 3: Louise Nevelson Plaza:
- Begin filling with grout.
Location 4: Maiden Lane (Water Street – Gold Street):
- Complete sidewalk on the south side and move to north side between Water and Pearl Streets
- Relocate existing utilities
- Shift to north side and begin excavation between Pearl and Gold Streets
|