|
*Last updated August 27, 2010
SATURDAY AUGUST 28, 2010
DAY: Work Shift is From 8:00 am to 3:00 pm
Operation #1 Re-installation of 1 sculpture
Location: Louise Nevelson Plaza
From: Liberty St. from William St. –Gold St.
SUNDAY AUGUST 29, 2010 (NO WORK)
DAY: Work Shift is From 9:00 am to 6:00 pm
MONDAY AUGUST 30, 2010
DAY: Work Shift is From 7:00 am to 7:00 pm
Operation #1 Restoration of sculpture A. Complete installation of granite pavers
Location: Louise Nevelson Plaza
From: Liberty St. from William St. –Gold St.
TUESDAY AUGUST 31, 2010
DAY: Work Shift is From 7:00 am to 7:00 pm
Operation #1 Restoration of sculpture A. Complete installation of granite pavers
Location: Louise Nevelson Plaza From: Liberty St. from William St. –Gold St.
------------------------------------------------------------------------------------------------------
William – Gold streets
No Thru-Traffic
8:00 AM-3:00 PM Saturday, August 28,2010
On Saturday August 28, 2010 from 8:00AM – 3:00 PM Liberty Street will be closed to through-traffic between William and Gold streets. The traffic restrictions are necessary for the crane operation to re install the newly restored Louise Nevelson Sculptures. The following are the traffic and pedestrian impacts:
Traffic Impacts:
- No Thru traffic
- Curbside parking will be eliminated during construction activities on either side of the street within the project limits.
- Garage access will be maintained
- Pedestrian access will be maintained at all time.
------------------------------------------------------------------------------------------------------
WORK ON LIBERTY STREET RECONSTRUCTION PROJECT PASSES 60 PERCENT MARK
The New York City Department of Design and Construction (NYCDDC) continues to manage the Liberty Street capital construction project. The project limits include Liberty Street between Nassau and Gold Streets, Maiden Lane between William and Water Streets and Pearl Street between Fulton and John Streets. In addition, Louise Nevelson Plaza is being reconstructed and sculptures restored.
WORK SCHEDULED: July–August , 2010:
Below is a list of work locations and activities to be completed:
Louise Nevelson Plaza:
- Install electric and plumbing lines
- Complete granite paver installation
- Complete restoration and reinstallation of sculptures
Maiden Lane (William– Water Streets):
Liberty St. (Nassau – William Streets):
- Install new curb and sidewalks on south side
- Final paving
- Install new street lighting throughout project
|