Liberty Street Reconstruction « back
Summary | Daily Activities | Contact Info | FAQs | Links

Liberty Street 
Liberty St. reconstruction began August 2008
As part of its plan to improve and update downtown’s infrastructure, the city  Department of Design and Construction (DDC) plans to launch the capital reconstruction of Liberty Street in summer 2008. The work will take place on Liberty Street (Nassau to Gold) extending the Liberty Street road reconstruction that was completed in 2007 west of Nassau.

The contract also will include Maiden Lane from William to Water Streets; Louise Nevelson Plaza at William and Liberty Streets; and Pearl Street from Fulton to John Streets.

For this Liberty Street project, city crews will excavate, update utilities, and restore the roadway. Together with the Lower Manhattan Construction Command Center, the DDC also will host periodic community stakeholder meetings.

Click here for a tour of the rebuilding projects taking place in Lower Manhattan.

Locate this project on the Interactive Streetwork Map.


Summary

Work is active at:

  • Louise Nevelson Plaza (at Liberty and William): Reconstruction began in early December 2008, including Con Ed utility work. 
  • Maiden Lane from William to Pearl: Reconstruction and utility work continues through spring 2010 in multiple segments.
  • Liberty Street from Nassau to William: Final sidewalk work will be performed upon removal of the scaffold on the south side, appx. December 2009

TRAFFIC ALERT: Maiden Lane is currently westbound-only; eastbound traffic is diverted to John via William Street.

WORK NOTICE: Starting Oct. 19, 2009, Con Edison steam crews to work overnight (midnight to 7 a.m.) to expedite work on Maiden Lane from Pearl to Gold St.  Noise at the work site will be limited.


Daily Activities

*Last updated November 20th, 2009

SATURDAY NOVEMBER 14, 2009 (NO WORK)

DAY: Work Shift Is From 8:00 am to 5:00 pm


SUNDAY NOVEMBER 15, 2009 (NO WORK)

DAY: Work Shift Is From 8:00 am to 5:00 pm


MONDAY NOVEMBER 16, 2009

DAY: Work Shift Is From 7:00 am to 7:00 pm

Operation #1 No work
Location: Liberty St.
From: Nassau St. – William St.

Operation #2 Substantially completed (No work)
Location: Pearl St.
From: John St. – Fulton St.

Operation #3 Drilling and Grouting operations
Location: Louise Nevelson Plaza
From: Liberty St. from William St. –Gold St.

Operation #4 Sidewalk and vault modification on north side
Location: Maiden Lane
From: Pearl St. – Water St.

Operation #5 Install road base, utility relocation continues
Location: Maiden Lane
From: Pearl St –Gold St. /Intersection

Operation #6 Utility relocation, road base curb and sidewalk
Location: Liberty Street
From: Gold St. - William St


TUESDAY NOVEMBER 17, 2009

DAY: Work Shift Is From 7:00 am to 7:00 pm

Operation #1 No work
Location: Liberty St.
From: Nassau St. – William St.

Operation #2 Substantially completed (No work)
Location: Pearl St.
From: John St. – Fulton St.

Operation #3 Drilling and grouting operations
Location: Louise Nevelson Plaza
From: Liberty St. from William St. –Gold St.

Operation #4 Sidewalk and vault modification on north side
Location: Maiden Lane
From: Pearl St. – Water St.

Operation #5 Install road base, utility relocation continues
Location: Maiden Lane
From: Pearl St –Gold St. /Intersection

Operation #6 Utility relocation, road base curb and sidewalk
Location: Maiden Lane
From: Gold St. - William St.

 

------------------------------------------------------------------------------------------------------

NO MAJOR CONSTRUCTION ACTIVITIES TO OCCUR IN THE FOLLOWING LOCATIONS:

 Liberty Street between Nassau Street and Gold Street
Maiden Lane between William Street and Water Street
Louise Nevelson Plaza
Monday, November 23, 2009 thru
Sunday, November 29, 2009

 Beginning on/about Monday, November 23, 2009, and continuing through Sunday, November 29, 2009, there will be no major construction activities occurring at the following locations: Liberty Street between William Street and Gold Street; Maiden Lane between William Street and Pearl Street; and, Pearl Street between John Street and Fulton Street. Work activities will resume on Monday November 30, 2009.

Traffic / Community Impacts:

We appreciate your cooperation and thank you for your patience while we rebuild Manhattan’s infrastructure.

------------------------------------------------------------------------------------------------------

The DDC Continues Work on Liberty Street

The New York City Department of Design and Construction (NYCDDC) is managing a capital construction project along Liberty Street between Nassau and Gold Streets, Maiden Lane between William and Water Streets and Pearl Street between Fulton and John Streets. In addition, the Louise Nevelson Plaza will be reconstructed.

 
WORK COMPLETED AS OF August 2009

Below is a list of work locations and activities that have been completed to date:

Location 1: Liberty Street (Nassau Street–William Street):

  • Final road paving

Location 2: Pearl Street (Fulton Street- John Street):

  • Final road paving

Location 3: Louise Nevelson Plaza:

  • Excavation of the sub-grade of the plaza.
  • Installation of the artwork piece “Rainbow conversations” on the fencing surrounding Plaza.

  

WORK SCHEDULED for September- October 2009:

Below is a list of work locations and activities slated to occur / to be completed:

Location 1: Liberty Street (Nassau Street–William Street):

  • Begin sidewalk replacement

Location 2: Pearl Street (Fulton Street- John Street):

  • Install street lighting.

Location 3: Louise Nevelson Plaza:

  • Begin filling with grout.

Location 4: Maiden Lane (Water Street – Gold Street):

  • Complete sidewalk on the south side and move to north side between Water and Pearl Streets
  • Relocate existing utilities
  • Shift to north side and begin excavation between Pearl and Gold Streets

 


Contact Info

For more information on the Liberty Street reconstruction project, please call community liaison Kisha Dasent at (212) 693-0295 or call 311. Stakeholders can submit questions or subscribe to email updates at FLD_HWMWTCA6C@verizon.net.


Frequently Asked Questions

Click here for answers to commonly asked construction questions.

Related Links

Maiden Lane Westbound-Only Starting March 14
Nevelson Plaza Sculpture Removal Begins
Get It Fast: Latest Advisories
Looking Ahead rebuilding projects
Special Feature
> Construction Lingo
> Construction Questions Answered
> Support the Memorial
> Envisioning the Future
Headline
- Three Questions for Rich Dalessio, Fiterman Hall
- Cortlandt St Northbound Subway Platform Reopens
- Washington and Carlisle to Close for Crane Removal
- BPC Site 23 Crane Removal to Close Warren Street
- Rector Street Utility Work Extended
- WTC Memorial Plaza on Schedule for 2011 Opening
Community Happenings

Current Construction | Programs in Lower Manhattan | Get It Fast Latest Advisories | News and Image Gallery | About the LMCCC
Home | Search | Fraud Prevention | Get Email Updates | Media Center | Information Library | Contact Us | Navigating This Site

© 2009 Lower Manhattan Construction Command Center/LMDC

RSS Feed - Really Simple Syndication RSS Feed