This work is part of the Beekman and Park Place Reconstruction Project
|
The city’s capital street reconstruction extends onto Nassau Street from Beekman to Spruce this week. An extension of the Beekman/Park Place Reconstruction project, the new segment allows crews to replace a degraded water main and upgrade other utilities in the Nassau roadbed over the next three months. One traffic lane will be maintained on weekdays during the project, but a full closure is in place on weekends, and parking is temporarily restricted. Weekday hours are 7 a.m. to 3:30 p.m.; weekend hours are 8 a.m. to 4:30 a.m. Local residents and businesses will be notified of water-service interruptions as they occur.
|